NOTIFICATION
Sub: Cancellation of Shutdown for 132kV Kurichu – Tintibi.
With reference to letter /Message No. 10/BPC/TD/SCO/10/Vol-I/026 dated January 28, 2010 the shutdown approval for 132kV Kurichu – Tintibi line, dated 05/01/10 to 07/01/10 is now cancelled. The same maintenance may be proposed later.

Your request for announcement of power supply interruption vide letter no.BPC/TMD/NK/TCEH-10/2010/25 dated January 29, 2010 to BBS Corporation, Trashigang may be immediately cancelled.

10/BPC/TD/SCO/10/Vol-I/ Date: 28/01/2010
Sub: Shutdown Approval for Annual Maintenance Plan.
With reference to letter /Message No. 72/TD/BPC/2K10/Vol-3/50 dated January 28, 2010 regarding annual line maintenance programme submitted to this office for eastern region is hereby approved as detailed below:
1. Shut down and Duration:
Sl. No. Name of Element Agency to Availing Shut- down From Date / Time To Date / Time Remarks
1 132kV Kurichu-Tintibi TMD, Nangkor, Gelephu, & Gyelpozhing 05/02/2010 (9:00)hrs 7/02/ 2010 (16:30)hrs On daily returnable basis
2 132kV Tintibi-Nganglam & 132kV Kilikhar-Kanglung TMD, Nangkor, & Gyelpozhing 26/02/2010 (9:00)hrs 28/02/ 2010 (16:30)hrs On daily returnable basis
3 132kV Nangkor-Nganglam & 132kV Kurichu-Kilikhar TMD, Nangkor, & Gyelpozhing 06/03/2010 (9:00)hrs 07/03/ 2010 (16:30)hrs On daily returnable basis