To reliably and efficiently wheel electricity for domestic consumption and export
STRATEGIES
1. Develop National Grid and tie-lines for export of electricity
| Measure | Targets | Initiatives | Ans. |
|---|---|---|---|
| System Study |
Establish base case model with fully reconciled network and load data by 2007 |
Interaction with all generating companies as well as Indian grid coordinator for true data of the Indian interconnections Establish system of reporting for new lines/ substations for timely update of system data Compute line parameters for various types/ configurations of lines in the system and reconcile with existing data |
TD, EDD |
| Simulation of multiple operating conditions with a view to establish adequacy of existing network for export/ augmentation for both export and internal tie-line establishment |
Establish feasibility of East – West interconnection through Tsirang- Gelephu tie- line (2008) Other studies with Punatsangchhu and Mangdechhu (2008) with alternative interconnections |
Data collection of Dagachhu, Punatsangchhu and Mangdechhu Prepare Load growth scenarios like industrial |
TD, EDD |
| Study system performance for future load scenarios with reference to the internal generation capability (seasonal) and propose measures for generation-load match for system operator guidelines by 2007 |
2. Establish System Operator functions and to contribute to the National wealth through optimal load dispatch planning
| Measure | Targets | Initiatives | Ans.> |
|---|---|---|---|
| System Coordination Setup |
Fully functional by 2007. |
Training for the system coordinators Follow-up & encourage employees designated as system coordinators to take ownership & commitment of the system Setup Database |
TD, EDD |
| System Operator Functions |
Fully functional by 2009 |
Establish NLDC |
TD |
3. Ensure efficient and reliable system performance
| Measure | Targets | Initiatives | Ans. |
|---|---|---|---|
| Streamline Operation & Maintenance procedures for Lines & Substation |
Establish benchmark for i) forced maintenance of lines and substation ii)system reliability, iii) plan for up-gradation and new investments including contingency requirements by 2008, Introduce Hotline Maintenance by 2008 |
Develop O&M manuals Carry out outages analysis to establish present level of reliability |
EDD, TD |