This is to notify all our valued customers and the general public that BEA has approved revision of miscellaneous charges for BPC vide letter no. BEA/CEO/BPC/2021-2022/148 dated 26 August 2021 as under. BPC shall implement the revision with immediate effect.

A) Meter Security
ParticularsExisting Rates (Nu)Revised Rates (Nu)
 Meter Security DepositCost of MeterShall be discontinued

B) Energy Security

Sl. No.Consumer CategoryExisting Rates (Nu)Revised Charges (Nu)
1 LV Single Phase (Rural)10/A5/A
2 LV Single Phase (Others) 10-60 A20/A20/A
3 LV Three Phase60/A60/A
4 LV Three Phase with CT Metering60/A60/A
5 Medium Voltage (MV)120/kVA rating of the transformer120/kVA rating of the transformer
6 High Voltage (HV)120/kVA rating of the transformer120/kVA rating of the transformer

C) Supply Reconnection Charges

Sl. No.Consumer TypeExisting Charges (Nu)Revised Charges (Nu)
1 LV Single Phase100100
2 LV Three Phase150200
3 Medium Voltage500200
4 High Voltage500200

D) New Service Connection Charges

Sl. No.Consumer TypeExisting Charges (Nu)Revised Charges (Nu)
1 LV Single Phase100For the initial supply release to a consumer premises no charges shall be levied for testing, connection and installation. However, consumer availing the services subsequently, shall be charged at the prevailing rate
2 LV Three Phase150
3 Medium Voltage500
4 High Voltage500

E) Capacity Reserve Charges

Sl. No.Consumer TypeExisting Charges (Nu)Revised Charges (Nu)
1 HV and MV customersEqual to demand charge for three months calculated on the conditionally sanctioned loadEqual to demand charge for three months calculated on the conditionally sanctioned load

F) Late Payment Surcharge

Sl. No.ParticularsExisting ChargesRevised Charges
1 All categories of customers2% per month of the billed amount2% per month of the outstanding billed amount non compounding