Bhutan Power Corporation Limited (BPC), Contract Management Section (CMS), hereby informs all prospective bidders that Amendment No. 1 has been made to the Bill of Quantities (BOQ) for the “Labour Contract of Plan Works, 2026 under Haa–Paro, Samdrup Jongkhar, and Dagana–Sarpang–Zhemgang Dzongkhags.” Specifically, BOQ Item No. 5.7.2.5.1.11, Providing and laying HDPE pipes including fittings (excluding trenching, refilling, and thrust blocks), has been revised to specify that the HDPE pipe size shall be 160 mm diameter. All prospective bidders are requested to take note of this amendment and incorporate the above revision while preparing and submitting their bids. All other terms and conditions of the Bidding Document shall remain unchanged.
Supply, Construction, Testing and Commissioning of Package I – Khorlochu to Durungri (1x400kV D/C ACSR twin Moose) & Package II – Durungri to Goling (1x400kV D/C ACSR twin Moose)
(Tender no: BPC/C&PD/CMS/TENDER-2026/17)
Following are the amendment made for the referred tender:
SECTION-9: Price Schedule
It is observed that, in Schedule I the formula is stipulated as follows:

Should be read as:

Supply, Construction, Testing and Commissioning of Package I – Khorlochu to Durungri (1x400kV D/C ACSR twin Moose) & Package II – Durungri to Goling (1x400kV D/CACSR twin Moose)
(Tender no: BPC/C&PD/CMS/TENDER-2026/17)
Following are the amendment made for the referred tender:
ITB 4.5: The Technical Qualification and the Financial Qualification Requirements are as follows:
(a) Technical
ii) Supply of towers
The Bidder should have its own manufacturing facilities for the Transmission Line towers and tower parts having the following minimum manufacturing capacities and manufacturing experience.
Should be read as:
ITB 4.5: The Technical Qualification and the Financial Qualification Requirements are as follows:
(a) Technical
ii) Supply of towers
The Bidder should have “access to” manufacturing facilities for the Transmission Line towers and tower parts having the following minimum manufacturing capacities and manufacturing experience.
Supply, Construction, Testing and Commissioning of Package I – Khorlochu to Durungri (1x400kV D/C ACSR twin Moose) & Package II – Durungri to Goling (1x400kV D/C ACSR twin Moose)
(Tender no: BPC/C&PD/CMS/TENDER-2026/17)
Following are the amendment made for the referred tender:
ITB 4.2: Qualification of the Bidder.
c) the Partner-In-Charge/Lead Partner shall meet all the Qualification Requirements by itself, and each of the other partners shall meet at least 25% of the technical or financial qualification requirements;
Should be read as:
c) the Partner-In-Charge/Lead Partner shall meet all the “Technical Qualification Requirements” by itself, and each of the other partners shall meet at least 25% of the technical or financial qualification requirements;
Supply, Construction, Testing & Commissioning of One No. 400kV D/C transmission line from Gamri II to Khorlochu Twin Moose (LILO one circuit of 1x400kV D/C Khorlochu to Durungri Line), One No. 220kV D/C transmission line from Tshephu to Gamri II (1x220kV D/C with ACSR Zebra) and One No. 220kV S/C transmission line from Gamri I to Gamri II (1x220kV S/C with ACSR Zebra)
(Tender no: BPC/C&PD/CMS/TENDER-2026/15)
Following are the amendment made for the referred tender:
ITB 4.5: The Technical Qualification and the Financial Qualification Requirements are as follows:
(a) Technical
As a minimum qualifying requirement, the bidder should have successfully carried out, as a prime contractor, the execution of at least one project of a similar nature and complexity in hilly areas comparable to the proposed project during the last ‘five years’ to be replaced by ‘tenyears’.
Should be read as:
ITB 4.5: The Technical Qualification and the Financial Qualification Requirements are as follows:
(a) Technical
As a minimum qualifying requirement, the bidder should have successfully carried out, as a prime contractor, the execution of at least one project of a similar nature and complexity in hilly areas comparable to the proposed project during the last ten years.