Supply, Construction, Testing & Commissioning of One No. 400kV D/C transmission line from Gamri II to Khorlochu Twin Moose (LILO one circuit of 1x400kV D/C Khorlochu to Durungri Line), One No. 220kV D/C transmission line from Tshephu to Gamri II (1x220kV D/C with ACSR Zebra) and One No. 220kV S/C transmission line from Gamri I to Gamri II (1x220kV S/C with ACSR Zebra)
(Tender no: BPC/C&PD/CMS/TENDER-2026/15)
Following are the amendment made for the referred tender:
ITB 4.5: The Technical Qualification and the Financial Qualification Requirements are as follows:
(a) Technical
As a minimum qualifying requirement, the bidder should have successfully carried out, as a prime contractor, the execution of at least one project of a similar nature and complexity in hilly areas comparable to the proposed project during the last ‘five years’ to be replaced by ‘tenyears’.
Should be read as:
ITB 4.5: The Technical Qualification and the Financial Qualification Requirements are as follows:
(a) Technical
As a minimum qualifying requirement, the bidder should have successfully carried out, as a prime contractor, the execution of at least one project of a similar nature and complexity in hilly areas comparable to the proposed project during the last ten years.
Supply, Construction, Testing and Commissioning of Package I – Khorlochu to Durungri (1x400kV D/C ACSR twin Moose) & Package II – Durungri to Goling (1x400kV D/C ACSR twin Moose)
(Tender no: BPC/C&PD/CMS/TENDER-2026/17)
Following are the amendment made for the referred tender:
ITB 4.5: The Technical Qualification and the Financial Qualification Requirements are as follows:
(a) Technical
As a minimum qualifying requirement, the bidder should have successfully carried out, as a prime contractor, the execution of at least one project of a similar nature and complexity in hilly areas comparable to the proposed project during the last ‘five years’ to be replaced by ‘10 years’.
Should be read as:
ITB 4.5: The Technical Qualification and the Financial Qualification Requirements are as follows:
(a) Technical
As a minimum qualifying requirement, the bidder should have successfully carried out, as a prime contractor, the execution of at least one project of a similar nature and complexity in hilly areas comparable to the proposed project during the last 10 years.
July 25, 2025
BPC/C&PD/CMS/TENDER-2025/29
The submission deadline for the Tender No. BPC/C&PD/CMS/TENDER-2025/29 (supply, erection, testing, commissioning and upgradation of one line bay at the existing 132kV substation at Yurmoo) is extended till 1400 hours, August 01, 2025. The Bids shall be opened at 1430 hours on the same date.
All other terms and conditions specified in the bidding documents shall remain unchanged.
Chief Manager
Contract Management Section
Amendment to the Labour Contract for Plan Work under ESD, Bumthang: Package A1:2024
- The existing Labour Contract for Plan Work under ESD, Bumthang: Package A1:2024 is now amended as follows:
- In the Bill of Quantities (BOQ), Serial No. 7, sub section a, the following correction is made:
Replace: “construction of substation (63kVA)”
With: “construction of substation (125 kVA)” - All other terms and conditions of the Labour Contract remain unchanged.