Substation Maintenance Division , Semtokha under Transmission Department, Bhutan Power Corporation Limited, would like to invite sealed bid for the Supply and Delivery of Annual Rate Contract 2022(ARC) as detailed below.
Sl.No | Tender No & Date | Tender Name | Bid Submission Date and Time | Opening of bids on the same day at: |
1 | BPC/TD/SMD/2022/47/191 dated April 29,2022 | Annual Rate Contract for supply and Delivery of Miscellaneous Items(electrical,civil & plumbing),Small T&P and furniture | 20th May 2022 (12:30 Hrs) | 15:00 hrs |
The Interested bidders may note and submit the details as per the bidding documents that can be downloaded from BPC website(www.bpc.bt) free of charge and should register with SMD Semtokha,BPC,Thimphu at or before 12:30 hours on 20th May 2022 with a written application together with the valid business license and tax clearance certificate to make the bid enforceable.
BPC invites sealed bids from the class categories of Bhutanese National with W4 (Power and Telecommunications) valid License and registered with the construction Development Board for construction of electricity distribution infrastructure works under the following
1.Right of Way (Row) clearing of Distribution Lines and casting of poles at Wangdue Dzongkhags.
2.Construction works associated with Extension of LT Overhead and UG Lines in and around Wangdue
For more details download the following NIQ.
This is to notify that the letter of intend is issued in accordance with the group standard bidding document work, Clause No. 12.1.
For further information, download the letter from the link below:
Letter of intents for Labour Contract for RoW clearing vide tender No. BPC/ESD/SJ/TECH-11/2022/04 dated on 11 March 2022.
TD/BPC/2022/Vol-1/60
The Transmission Services, Transmission Department, Bhutan Power Corporation Limited would like to invite sealed bids from eligible Large and Medium Class (W3) Bhutanese Contractors registered with Construction Development Board (CDB) having valid trade license and CDB certificate for the following work:
a) | Bids for | Construction of 2 Nos. G+2 Staff Quarter at Gomtu. (Estimated Cost: Nu. 34,587,474.00) | Construction of G+2 Staff Quarter at Nanglam. (Estimated Cost: Nu. 19,169,862.00) | Construction of G+2 Staff Quarter at Yurmoo. (Estimated Cost: Nu. 19,087,588.00) |
b) | Bid security | Nu. 692,000.00 | Nu. 384,000.00 | Nu. 382,000.00 |
c) | Cost of bid document | Nu. 3,000/- (Non-refundable) | Nu. 1,500/- (Non-refundable) | Nu. 1,500/- (Non-refundable) |
d) | Contractor Class | Large (W3) | Medium (W3) | Medium (W3) |
e) | Date of sale | 23.04.2022 – 24.05.2022 | ||
f) | Date of submission | 24.05.2022 (On or before 12:00 hrs) | ||
g) | Date of opening | 24.05.2022 (14:30 hrs onwards) | ||
h) | Venue for opening | BPC Conference Hall, Thimphu |
Interested bidders may purchase the complete set of bidding document from Transmission Department (Third floor), BPC Head Office, Thimphu upon submission of written application along with copies of valid trade license, CDB registration certificate and Tax clearance certificate to the General Manager, Transmission Department, BPC, Thimphu on or before 24.05.2022 during working hours. Bidding documents can also be downloaded from www.bpc.bt. The bidder who have downloaded the bid document and wish to participate should register with GM, TD, TS, BPC, Thimphu with registration fee of Nu. 200.00, prior to the closing of bid sale date. For any other queries, contact Mr. Dorji Kinley, Executive Engineer at +975 2 322046 / 17117848. The scope of work includes following: – Site grading works. – Demolition of existing temporary sheds and aged bungalows. – Construction G+2 RCC framed structure with AAC block infill walls.Internal electrification works and street lighting. – Indoor and outdoor Plumbing and sanitary works.RRM walls, parking, and road works. – Other work as per the Bid document. |